Normalise the quotations
- 1
Issue the same information
Provide drawings, structural information, surveys, finish schedules and known constraints to every bidder.
- 2
Create a scope matrix
Compare demolition, structure, materials, access, services, making good and documentation line by line.
- 3
Expose uncertainty
List provisional sums, allowances, exclusions and hidden-condition assumptions.
- 4
Compare programme and payment basis
Understand sequencing, dependencies, milestones, VAT and when variations become payable.
- 5
Resolve gaps before appointment
A clarification added to one quote must be reflected across the comparison.
Where apparently similar quotes diverge
| Heading | Check whether it includes | Typical hidden difference |
|---|---|---|
| Demolition and structure | Protection, removal, structural information and waste | Only the new construction is priced. |
| Access and scaffold | Design, duration, licences or neighbour assumptions where relevant | A generic allowance ignores the site. |
| Services | Plumbing, drainage, electrical work, testing and coordination | Specialist trades are excluded or provisional. |
| Making good and finishes | Plaster, flooring, joinery, decoration and external reinstatement | The quote stops before a usable finished room. |
| Hidden conditions | Opening-up rules, provisional items and approval | Unknowns are either honestly stated or silently omitted. |
| Programme | Lead times, access, weather assumptions and trade dependencies | A duration is quoted without stating what can delay it. |
Structural information should be identifiable
Where work relies on engineering or other design, the quotation should state which drawings, revisions and specifications it uses. Builders should not be compared against different structural scopes. If the design is incomplete, that limitation should be visible rather than buried in a low total.
The existing general building quotation guide explains materials, drainage, foundations, access, VAT and allowances. This page adds renovation-specific demolition, services, finishes and concealed conditions.
Payments and variations
No universal deposit or stage percentage suits every project. Scale, bespoke materials, contract structure and sequencing matter. Use the DC Trades staged-payment guide to compare milestones, records, material payments and approval of additional work.
Questions homeowners often ask
Why is the cheapest renovation quote sometimes incomplete?
It may exclude design, services, access, making good, finishes or hidden-condition risk.
Should all unknown work be given a fixed price?
Not always. Concealed conditions may require a defined investigation and transparent provisional route.
Is one payment schedule correct for every project?
No. The project scale, materials and contract determine a suitable arrangement.